Project at Lundbeck A/S Lumsås where the existing process plant in synthesis factory F2 was upgraded with a new synthesis unit consisting of a reactor source, a reactor and a condenser. In connection with the upgrade the new synthesis unit had to be supplied with panels for managing valves and general control of the sources, the reactor and the condenser.

Tank in een productieomgeving bij een farmaceutische klant, waar we hebben gewerkt aan de uitbreiding van de syntheseproductie in de bestaande synthesefabriek F2

Vaardigheden

Stuurgroep
Project management
Project/Ontwerp Ingenieur
Specialistische competenties
Tekenhulpmiddel

Project fasen

Feasibility study
Conceptual design
Basic design
Detailed design
Installation
Commissioning & handover

The process

Lundbeck was responsible for the overall project management, HAZOP, mechanical installation of components as well as for qualification of the new process equipment. Process Engineering reported to the project manager from Lundbeck and provided consulting services on process and electricity/SRO in relation to the process plant, the electricity supply and CE marking. In addition, we prepared an ATEX report about the entire installation.

In order to streamline the process, and in partnership with Lundbeck, we focused on how the tests performed during qualification could be integrated in the CE marking.

Service and scope of the project

Heb je een project waarvoor je sterke technische vaardigheden nodig hebt?

Neem contact met ons op en ontdek hoe wij je kunnen helpen als consulting engineering partner.

Erik Kuiper
Neem contact met mij op voor meer informatie
Erik Kuiper
Country Manager the Netherlands

Book et møde