Preparation of CE marking manual

Kompetencer

Styregruppe
Projektledelse
Projekt/designingeniør
Specialistkompetencer
Tegneressourcer

Projektfaser

Feasibility study
Conceptual design
Basic design
Detailed design
Installation
Commissioning & handover
Neem contact met mij op voor meer informatie
Poul B. Jakobsen
CEO en eigenaar
Telefoon: +45 2424 1183

Project description

HOFOR is involved in various different business areas such as supply of electricity, water, heating, refrigeration, town gas, etc. plus handling of waste and wastewater. The assignment was to set up a common procedure in the form of a manual for handling the CE marking directive, which was later to be implemented in the organisation.

The process

Process Engineering’s project manager and specialists completed a range of interviews in the HOFOR organisation with key figures about the use of the CE marking directive. In this way we uncovered how the directive was already implemented in the organisation at the beginning of the project, and we also uncovered which special circumstances we had to take into account in the various areas.

On the basis of the interviews we prepared a manual that makes it possible to use the same principles across the entire HOFOR organisation. We educated the same key figures in the use of the manual through a series of workshops.

Service and scope of the project

Our service and the scope of the project include:

  • Project management
  • Process flow diagram
  • Mass balance
  • PI diagram
  • Inventories
  • Process descriptions
  • ATEX zones
  • Machine plan
  • Tender material and requirements specification
  • Purchasing and goods reception
  • Inspection, test and control of equipment
  • Installation tender
  • Safety coordination
  • Installation management
  • CE marking